Mulch & Mortar

Concrete calculator

Measure the pour, pick a shape, and this calculator gives you the volume in cubic yards plus the number of bagged mix to buy. It also shows when a ready-mix truck makes more sense than bags.

ft
ft
in
4 in for patios and walkways, 5 to 6 in for driveways.
in
ft
qty
ft
in
in
qty
$
$

Results update as you type. Nothing is sent anywhere.

How the concrete calculator works

Concrete is sold by volume. The calculator converts your measurements into cubic feet, adds a waste allowance, then divides by 27 to get cubic yards, which is how ready-mix suppliers price it. For bagged mix it divides the same volume by the yield printed on the bag.

Bag yields used here match the figures printed on Quikrete and Sakrete products: an 80 lb bag makes about 0.60 cubic feet, a 60 lb bag 0.45, and a 40 lb bag 0.30.

Formula

cubic yards = (length ft × width ft × thickness in ÷ 12) ÷ 27

bags = cubic feet ÷ yield per bag, rounded up to a whole bag.

Worked example: a 10 × 12 ft patio at 4 inches thick is 10 × 12 × 0.333 = 40 cubic feet. With 10 percent waste that is 44 cubic feet, or 1.63 cubic yards. In 80 lb bags, 44 ÷ 0.6 = 74 bags, weighing almost 3 tons. That is a clear case for ordering ready-mix.

Tips before you pour

Common sizes, already worked out

Common questions

How many 80 lb bags of concrete are in a cubic yard?

45 bags. A cubic yard is 27 cubic feet and each 80 lb bag yields 0.60 cubic feet, so 27 ÷ 0.6 = 45. It takes 60 of the 60 lb bags or 90 of the 40 lb bags.

How thick should a concrete slab be?

4 inches is standard for patios, walkways, and shed floors. Use 5 to 6 inches for driveways and anything that will carry a vehicle, and add rebar or wire mesh for spans over about 10 feet.

How much does a cubic yard of concrete weigh?

About 4,000 pounds, or 2 tons. Each 80 lb bag of mix weighs 80 pounds dry and a bit more once water is added, so the bag count here is a good proxy for what you will be lifting.

Is it cheaper to buy bags or order ready-mix?

Bags cost less for small jobs under about half a yard, since there is no delivery fee. Above a yard, the cost per cubic yard of bagged mix is typically two to three times the ready-mix price, before counting your time to mix 45 or more bags.